Waste Water Treatment Plant Al Kharj in Saudi Arabia

01.01.2016

Environmental Technology

As a part of Al Kharj Industrial city (AKIC), MODON has designed an activated sludge process based Wastewater Treatment Plant built up in 6 different phases.

The location of Al Kharj Industrial city is in the central Arabian Peninsula in the Kingdom of Saudi Arabia(KSA) around 30km south from Al Kharj.

The preliminary total-design is for 60.000m³/day, starting with phase 1 which covers 10.000m³/day.

Later on further phases will be built up depending on the actual growing of population and necessity.

 

RESCHREITER ENERGIETECHNIK delivered for this project the medium voltage cabinets, battery cabinet, transformer, diesel generator, the entire power and control distribution, as well as the Installationsmatrerial for the whole electrical installation. Also the programming, visualization and the control system are created by RESCHREITER ENERGIETECHNIK.

Supplied via a medium-voltage system (RING MAIN UNIT) designed for 13.8kV/60Hz, the distribution to a second RMU, from which a transformer 2500kVA/380V/60Hz is supplied. This transformer is used as the main supply of low-voltage panels.

For emergency power a diesel generator with 1535kVA/380V/60Hz is used.

The low-voltage system, carried out in conventional FIX mounting technic, consists of four main parts, which are distributed according to the system. The control of the equipment works via DOL, FC or softstarters.

Via a SCADA system based on WinCC, a completely easy control of the system is possible.

The operation is based on Siemens S7-400H (high-availability) and Remote I/Os ET200M, the different stations are connected by fiber optic cable.

In the CCR ( Central Control Room ) you will get an overall view of the whole plant on basis of a 4x2m large MIMIC created in digital printing technology.

 

Project name WWTP AL KHARJ INDUSTRIAL CITY
Project type Waste Water Treatment Plant
Location AL KHARJ / KSA (Kingdom of Saudi Arabia)
Scope of supply Engineering, switchgears MV/DC/LV, transformer, Diesel generator, installation, programming, commissioning
MV distribution SafePlus VVV ( RMU1 / RMU2 ) each 3 panels gasisolated, 1x Meteringpanel MT
Transformer Oiltransformer ( hermetic sealed ) 2500kVA/13.8kV0.38kV/60Hz/Dyn5
LV distribution MEHLER TRM ECONOMIC / RITTAL TS8 / FIX mounting technique ( 40 panels )
Generator SDMO Diesel Generator 1535kVA/380V/60Hz
Bus-bar HSC2A 4000A, 5p (3P+N+PE), Aluminium
Fields FIX;  40 panels – total length 39m
Compensation -
PLC control Siemens S7-400H / ET200M
I/O points 1260 I/O’s digital / 210 I/O’s analogue / 3 Bus – measurements
SCADA WINCC System Software V7.3 / ACRON V8 / 21 SCADA pictures
Communication Ethernet – fibre optical cable ; Ethernet CAT6 ; Profibus DP
USV Anlage EATON 9SX 5 kVA
E-Installation Control- and power installationmaterial and engineering of the whole plant, FOC und Ethernet cabling / Profi BUS cabling for the entire control system
Project status 2016 commissioning of plant

 

Scope of delivery and performance characteristics:

  • MV-plant gasisolated 17,5kV incl. Metering panel, powerdatas transmitted via PAC4200
  • Transformer 2500kVA/13.8kV/0.38kV/60Hz
  • Diesel Generator 1535kVA/380V/60Hz
  • LV-plant include 40 panels FIX-mounting syste
  • The entry points are 1 x 4000A circuit breaker, as well as 1 x 3200A generator circuit breaker
  • Operation of the devices takes place through DOL, FC, SOFTSTARTER
  • The fibre optic data network consists of several PLC stations, via which the whole data management for all equipment is transmitted.
  • The company RESCHREITER ENERGIETECHNIK has delivered and engineered the whole electrical installation material for the mechanical part of the plant, for the total measurements, as well as the data network